Start by ranking SKUs into three tiers: two hero SKUs that carry 70-80% of first-order volume, two to four validation SKUs at the lowest MOQ the line allows, and one or two seasonal tests.
Ask for MOQ per SKU per formula, not per order, because baby care MOQs are usually driven by fill volume and component minimums such as bottles, pumps, and caps.
Consolidating SKUs onto one bottle family and one cap size typically lowers MOQ and shortens lead time.
Sequence sampling before volume commitment.
Request pre-production samples for texture, scent, and pack compatibility, and allow roughly 10-15 working days for formulation samples plus stability and compatibility checks.
For the EU, confirm which documents you need early: CPSR, product information file support, safety assessment, microbiological and challenge testing, heavy metal and allergen screening, and labeling review.
We can support documentation and testing coordination, but approval timelines sit with your assessor and notified bodies.
Build the inventory plan around lead time gates rather than a single delivery date.
Typical production is 25-35 working days after sample approval and deposit, plus 25-35 days sea freight to EU ports, so plan safety stock for 6-8 weeks of sell-through.
Reserve 15-20% of budget for reorders on the winning SKU, and hold the test SKUs on air freight only if launch dates are fixed, since pressure changes raise leakage risk on pumps and flip caps.
Finally, align packaging with the inventory plan: standard bottles and caps reduce MOQ and rework, while custom decoration adds 7-15 days and raises minimums.
Confirm artwork, dielines, and label substrate before mass production to avoid humid-season bubbling and reprint costs.